Councils › Fermanagh and Omagh › LA10/2023/1605/F
Proposed Battery Energy Storage System (BESS) facility access substation building landscaping lighting/CCTV columns sec…
- Reference
- LA10/2023/1605/F
- Status
- CONSULTATION(S) ISSUED
- Application type
- Full
- Location
- Lands approximately 160m North West of No. 80 Doogary Road Omagh BT79 0BJ
- Council
- Fermanagh and Omagh District Council
- Received
- 30 Mar 2023
- Added
- 30 Mar 2023
Full proposal: Proposed Battery Energy Storage System (BESS) facility access substation building landscaping lighting/CCTV columns security fencing and ancillary development
Recent applications nearby
- LA10/2026/0670/A Case Officer Recommendation
1 Other - Wall Mounted Double Sided Sign
- LA10/2026/0428/DC Decided
Discharge of condition 1 (drainage discharge rate) and condition 2 (attenuation calculation) of planning approval LA10/2025/0644/F (storage extension to factor…
- LA10/2026/0347/A APPLICATION WITHDRAWN
1 Other - Free Standing Double Sided Sign
- LA10/2025/1007/F Approved
Proposed Battery Energy Storage System (BESS) facility (amendment to previously approved BESS LA10/2023/1605/F including access substation building landscaping…
- LA10/2025/0959/F Case Officer Recommendation
Amended siting and design of previously approved units approved under LA10/2021/1469/F and & proposed 2 No additional units.
- LA10/2025/0644/F Approved
Proposed storage warehouse extension to existing factory.
- LA10/2025/0489/F Approved
Extension to provide additional chill storage dispatch bays workshop/plant room relocation of existing lorry parking area new entrance into staff carparking.
- LA10/2025/0072/F Approved
Retention of retaining walls extension to yard and all weather recreation area all ancillary to the existing use of the dwelling