Councils › Fermanagh and Omagh › LA10/2017/0984/DC

Discharge of conditions nos. 8 (Bird Nesting Season) and 9 (Vegetation Retention) of planning approval LA10/2016/0124/F…

Construction of a new 110/33kV cluster substation located approximately 300m NE of 166 Dooish Road Drumquin. Construction of a new 110kV switching substation located approximately500m NNE OF 110 Cavan Road Dromore. Construction of approximately 8.6km of 110kV overhead transmission line to connect the two substations. This will traverse the townlands of Cavan Mullawhinny Shanneragh Mullaghbane Aghadulla (Harper) Corrasheskin Cornavarrow and Curraghamulkin
Reference
LA10/2017/0984/DC
Status
Granted
Application type
Discharge of Condition
Location
Construction of a new 110/33kV cluster substation located approximately 300m NE of 166 Dooish Road Drumquin. Construction of a new 110kV switching substation located approximately500m NNE OF 110 Cavan Road Dromore. Construction of approximately 8.6km of 110kV overhead transmission line to connect the two substations. This will traverse the townlands of Cavan Mullawhinny Shanneragh Mullaghbane Aghadulla (Harper) Corrasheskin Cornavarrow and Curraghamulkin
Council
Fermanagh and Omagh District Council
Received
21-Sep-17
Added
21 Sept 2017

Full proposal: Discharge of conditions nos. 8 (Bird Nesting Season) and 9 (Vegetation Retention) of planning approval LA10/2016/0124/F (Substation)