Non-material change to planning application ref no T/2015/0094/F (solar farm). Change dimensions and design of approved…
- Reference
- LA03/2016/0192/NMC
- Status
- Granted
- Application type
- Non Material Change
- Location
- Land 90m West of and lands to the South of 72 Milltown Road Antrim
- Council
- Antrim and Newtownabbey Borough Council
- Received
- 29-Feb-16
- Added
- 29 Feb 2016
Full proposal: Non-material change to planning application ref no T/2015/0094/F (solar farm). Change dimensions and design of approved DNP substation to comply with the DNO substation specification required by NIE
Planning history at this location
10 other applications recorded at or next to this site.
- LA03/2019/0028/NMC Granted
Non-material change to planning permission LA03/2016/0643/F (Installation of Solar Farm) comprising: (a) change to the location of the panel arrays; (b) altera…
- LA03/2018/0266/NMC Granted
Non-Material Change to Planning approval T/2015/0094/F (Installation and operation of a solar farm and associated infrastructure for the life of the solar farm…
- LA03/2016/0677/NMC Granted
Non-Material Change to Planning approval LA03/2016/0226/F (Solar farm). The provision of detailed elevations for proposed client sub-station and auxiliary tran…
- LA03/2016/0631/DC Granted
Discharge of Condition 02 (Archaeological Programme of Works) for planning approval T/2015/0094/F (Installation of solar farm)
- LA03/2016/0643/F Granted
Variation of Condition 08 of Planning Approval T/2015/0094/F (Installation of Solar Farm) regarding time for site restoration and submission of restoration pla…
- LA03/2016/0583/DC Refused
Discharge of Condition 8 (decommissioning and restoration plan) of Planning Approval T/2015/0094/F for solar farm
- LA03/2016/0375/DC Granted
Discharge of Condition 10 (Programme of maintenance) of Planning Approval T/2015/0094/F for Solar farm
- LA03/2016/0226/F Granted
Solar farm (vary condition 9 re: finishes of supporting structures for solar panels) approved under T/2015/0094/F
- LA03/2016/0159/DC Granted
Discharge of Condition 10 (Programme of Maintenance) of planning approval T/2015/0094/F for Installation and operation of a solar farm and associated infrastru…
- T/2015/0094/F Granted
Installation and operation of a solar farm and associated infrastructure for the life of the solar farm (Additional Information)