Councils › Causeway Coast and Glens › LA01/2021/1486/NMC
Construction of a wind farm comprising 9no wind turbines (maximum 149.9m meters to blade tip) and associated infrastruc…
- Reference
- LA01/2021/1486/NMC
- Status
- Refused
- Application type
- Non Material Change
- Location
- Lands approx. 6km N E of Limavady accessed off Broad Road in the Townland of Gortcorbies
- Council
- Causeway Coast and Glens Borough Council
- Received
- 03-Dec-21
- Added
- 3 Dec 2021
Full proposal: Construction of a wind farm comprising 9no wind turbines (maximum 149.9m meters to blade tip) and associated infrastructure including external electricity transformers crane hardstandings underground cabling control building substation compound newly created site entrance new and upgraded on-site access tracks turning heads and all other associated ancillary works. During construction and commissioning there will be a number of temporary works including a construction compound with car parking temporary parts of crane hardstanding and welfare facilities. Planning consent was granted 17th December 2020 (LA01/2018/0200/F)
Planning history at this location
3 other applications recorded at or next to this site.
- LA01/2026/0085/DC CONSULTATION(S) ISSUED
Condition Discharge application of Conditions 21 23 24 26 28 29 33 34 & 35 of LA01/2022/0981/F and LA01/2024/1430/F for Dunbeg South Wind Farm
- LA01/2024/1430/F Approved
Variation of Condtion 14 (Noise Limit) of Planning Approval LA01/2022/0981/F (Wind Farm)
- LA01/2024/1368/S54 CONSULTATION(S) ISSUED
Variation of Condition 14 (Noise Limits) of Planning approval LA01/2022/0981/F (Wind Farm).