Councils › Causeway Coast and Glens › LA01/2019/0890/F

The Repower of the existing Rigged Hill Windfarm comprising the following main components; (i) Decommissioning of the e…

Existing Rigged Hill Windfarm site 6km East/South East of Limavady
Reference
LA01/2019/0890/F
Status
Granted
Application type
Full
Location
Existing Rigged Hill Windfarm site 6km East/South East of Limavady
Council
Causeway Coast and Glens Borough Council
Received
02-Aug-19
Added
2 Aug 2019

Full proposal: The Repower of the existing Rigged Hill Windfarm comprising the following main components; (i) Decommissioning of the existing 10 turbines (ii) Removal and restoration of the existing substation building and compound (iii) Removal and restoration of other redundant infrastructure (iv) 7 No. wind turbines with an output of around 29MW (v) Construction of approximately 4.82km of new access tracks; (vi) Upgrade of approximately 1.75km of existing access tracks; (vii) Construction of temporary and permanent hardstanding areas for each turbine to accommodate turbine component laydown areas crane hardstanding areas and external transformers and/or switchgears; (viii) Temporary construction compound/laydown areas; (ix) Turning heads and passing places incorporated within the site access infrastructure; (x) New Road Junction with Terrydoo Road; (xi) Meteorological Mast; (xii) Substation with roof mounted solar panels and associated compound (xiii) Removal of self-seeded trees in East of the Site and (xiv) all associated ancillary works.

Planning history at this location

4 other applications recorded at or next to this site.

  • LA01/2024/1148/DC CONDITION PARTIALLY DISCHARGED
    Discharge of condition 33 of LA01/2019/0890/F
    Existing Rigged Hill wind farm site 6km East/South-East of Limavady · 18 Oct 2024
  • LA01/2024/1023/DC CONDITION PARTIALLY DISCHARGED
    Discharge of Condition 29 of LA01/2019/0890/F
    Existing Rigged Hill wind farm site 6km East/ South-East of Limavady · 16 Sept 2024
  • LA01/2024/0973/DC Decided
    Discharge of Condition 23 of LA01/2019/0890/F
    Existing Rigged Hill wind farm site 6km east/ south-east of Limavady · 30 Aug 2024
  • LA01/2024/0972/DC CONDITION PARTIALLY DISCHARGED
    Partial Discharge of Condition 26 (parts A B C D E F & G) of LA01/2019/0890/F
    Existing Rigged Hill wind farm site 6km east/ south-east of Limavady · 29 Aug 2024