Construction and operation of a solar farm with a total generating capacity of 25mw. Development comprises photovoltaic…
- Reference
- LA01/2016/1217/NMC
- Status
- Granted
- Application type
- Non Material Change
- Location
- Lands surrounding 25 and 25a Tullaghans Road Ballymoney. Land begins at approx. 430m South of 27 Tullaghans Road approx. 280m West of 89 Mullan Road approx. 600m North of 15 Slievenaghy Road and approx. 360m South East of 190 Finvoy Road.
- Council
- Causeway Coast and Glens Borough Council
- Received
- 07-Oct-16
- Added
- 7 Oct 2016
Full proposal: Construction and operation of a solar farm with a total generating capacity of 25mw. Development comprises photovoltaic panels mounting frames 1 no. substation 20 no. inverter stations 12 no. CCTV cameras ( 3 metres high ) and ancillary construction works including perimeter fencing ( 2.4m high ) internal service tracks and 1 no. temp construction compound.
Planning history at this location
2 other applications recorded at or next to this site.
- LA01/2023/1238/NMC Approved
Modification of approved scheme to provide addtional internal access tracks.
- LA01/2015/1045/F Granted
Construction & operation of a solar farm with a total generating capacity of 25MW. Development comprises photovoltaic panels mounting frames 1 no. substation 2…